Andrew County seeks USDA option for jail funds

SAVANNAH, Mo. - Andrew County found a possible financial solution Monday for a new jail, even though there are still questions.

"If we can't do it in 60 days, then we don't need to do it," said Dick Townsend, a former county commissioner and local farmer.

A big hurdle may have been overcome thanks to the U.S. Department of Agriculture's Rural Development Program.

The USDA could loan the county all $5.5 million at a current rate of 4.25 percent for as long as 40 years if the paperwork checks out, said Neal Miller, area director. The funds would come from stimulus money, he said.

Before anything can happen, Larry Goldberg needs to complete and file a feasibility study with the county, said Larry Atkins, Andrew County presiding commissioner.

Mr. Goldberg is the architect who developed the jail plan based on his company's experience, the county's desire that there be no additional taxes, federal minimum standards and Sheriff Bryan Atkins' safety requirements for employees and prisoners.

That feasibility study would have to be reviewed by Helen Taylor, an independent CPA hired to review the project's figures for the county and the ad hoc jail committee. Then it would be forwarded to USDA to ensure the plans meet standards for a loan.

The committee was told that the county received three land proposals. While no official action has been taken, a review suggests that the commissioners are considering land south of Main Street and north and east of the fire station on U.S. Business Highway 71. It's also land that the city has expressed interest in acquiring.

If the county obtains an agreement to purchase any property, the USDA will do an environmental study.

The county commissioners and the sheriff left the jail committee meeting so that the seven members could talk in private.

Mr. Townsend said that when he was first appointed to the jail committee he was 95 percent against a new jail. Now, the cost and financing are no problem, Mr. Townsend said. The former commissioner said he knows one federal lawsuit could cost the county enough money to build four jails.

"But I do have a problem," he said. "My problem is the future operating cost."

The county and the ad hoc committee plan to continue meeting and studying all the issues.

Marshall White can be reached at marshall@npgco.com.

Share Your Thoughts

Comments are the sole responsibility of the person posting them. We do not review every post or respond to every removal suggestion. Comments that threaten someone or degrade them on the basis of gender, race, class, national origin, religion or disability will be removed. Comments containing abusive, vulgar or sexually-oriented language will be removed. Comments that spread rumors or lies will be removed. Please discuss only what has been factually proven. Comments posted in all caps will be removed. Stay on topic! Brief quotes are okay as long as the source is given. Blatant cutting and pasting is not acceptable. Comments must be kept under 250 words or less. Stjoenews.net moderators also reserve the right to remove comments for any reason they deem worthy. Click here for our full user agreement.